Project case study / Lindfield, NSW
Former Woolworths complex
Steel structures dismantled and scrap recovered from a constrained suburban site.
361 tmetal recovered
11days on site
2shear excavators
2021project delivery
The challengeA recovery plan
A recovery plan
built around the site.
Weather delays, specialist contractor sequencing, school-zone transport restrictions and a three-storey steel structure required careful coordination with the demolition team.
One coordinated approach.
- Mobilise two shear-equipped excavators and experienced operators.
- Dismantle steel structures and separate ferrous and non-ferrous material.
- Use lidded bins for secure storage of higher-value material.
- Schedule transport around permitted access windows and changing site conditions.
The recovery outcome.
Approximately 350 tonnes of steel and 11 tonnes of non-ferrous metal were recovered, with Top Dollar’s on-site scope completed in 11 days.
Keep exploring
More of our work
Coles–Linfox Distribution Centre
A coordinated metal-recovery program for a large industrial demolition.
Toyo Tyres industrial demolition
Structural steel recovered as the former Toyo Tyres facility made way for a logistics precinct.
North Strathfield
Staged industrial demolition beside occupied residential buildings.
It starts with a conversation
Request a site assessmentLet’s keep your next project moving.
You don’t need to know every grade. Tell us about your material and we’ll help you work out the next step.